JR Central to scrap year-end target for maglev opening date

The operator had promised a timeline for the Linear Chuo Shinkansen by the end of the year, but construction setbacks have pushed the announcement back.

By Newsroom1 min read
JR Central to scrap year-end target for maglev opening date
The lead car of the "L0 Series improved test train" running on the Yamanashi maglev test line, in Ogarayama, Tsuru, Yamanashi Prefecture, on October 8, 2021. Asahi Shimbun (x)

JR Central will abandon its plan to announce a projected opening date for the Linear Chuo Shinkansen — the maglev line meant to link Tokyo and Nagoya — within the year, sources familiar with the matter told the Asahi Shimbun, with President Shunsuke Niwa expected to explain at a news conference in Nagoya on the 18th.

At a news conference on the 12th, Niwa had said the company was still studying the timing. "We are proceeding on the assumption we will present it within the year," he said then.

The schedule has slipped on several fronts. Taisei Corporation, the major contractor handling the Shizuoka construction section, has been handed a business suspension order, and JR Central has said it will hold off on work it had planned to start in Shizuoka within the year.

The company has also disclosed damage at a tunnel site in Shinagawa Ward, Tokyo, where parts of a shield machine — the boring device used to cut the tunnel — were chipped. Construction of the new Nagoya Station is running behind schedule as well. The company appears to have concluded that it needs to review the timing of its forecast in light of these conditions.

Under the original plan approved by the minister of land, infrastructure, transport and tourism in 2014, JR Central aimed to open the line in 2027. Construction has been delayed by environmental concerns in the Shizuoka section, and the company has been forced to give up that target.